Complete list of Battery Energy Storage System (BESS) projects that have received Technical Connection Approval (ATR - Aviz Tehnic de Racordare) for grid connection in Romania. Data compiled from Transelectrica, DSO reports, and public sources.
| Project | Developer | MW | MWh | County | Status | Expected COD | Connection |
|---|
ATR (Aviz Tehnic de Racordare) is the Technical Connection Approval issued by grid operators (Transelectrica for 110kV+ or DSOs for lower voltages) that confirms a project can connect to the electricity grid at a specific point with approved capacity.
Data compiled from: Transelectrica CRD Maps, Economica.net, DSO public lists, and regulatory filings. Last updated: December 2025.
Romania has one of Europe's largest BESS pipelines relative to system size. With ~8.6 GW of ATR capacity versus ~6 GW peak load, battery storage will play a critical role in grid flexibility and renewable integration.
This list may not be complete. ATR approval does not guarantee project completion. Some projects may be cancelled, delayed, or modified. For official information, contact Transelectrica or relevant DSOs directly.